City of Helena Water & Sewer Project
Start Date: April 2020
Completion Date: September 2021
The project consisted of installing a new 8” Water Main, 14” Water Main, and a 8” Sewer Main. During the installation of the new water mains, 29 new Fire Hydrants were installed and 276 new water services to individual residences for future or continued water service. Throughout the installation of the new sewer mains, 53 (ea) 48” and 4 (ea) 60” Manholes were installed and 230 individual sewer services to individual residences.
Additional work included the extension of Knight Street, allowing Knight Street from Elizabeth Street through to Silverette Street.